Dear Member,
Summer grid shutdown and Ethex onboarding update.
Further to our last update on 13th July, this member newsletter summarises developments since then and responds to questions raised by members.
We are receiving a high volume of emails from members who are understandably concerned about the impact of the grid shut down. We do read all emails sent to us but are unable to respond individually to all of them. We do our best to address the questions raised in these newsletters.
The vast majority of emails we receive from members are constructive and raise sensible questions, suggestions and concerns that are of interest to all members. Most members recognise the shut down is not the fault of Derril Water Solar Co-op’s volunteer board and new managing agents. The grid shut down comes on top of the construction delay and Ripple going into administration.
We have provided a glossary of technical terms and the various electricity network operators involved at the bottom of the newsletter.
Headlines
-Derril Water Solar remains off-line due to an area-wide grid shut down.
-Active network management measures being introduced by the distribution network operator in August may allow partial export.
-Voltage compensation generators commissioned by the network operators are due to come online in September and will further reduce the constraint.
-The 4 month grid shut down through the summer generation period will have a significant impact on this year’s revenues. There will not be sufficient funds to make the planned member savings payments in August 2026 or February 2027.
-We are waiting on confirmation of the likely long-term grid curtailment to determine what the outlook is for bank loan affordability and member payments.
Response to questions raised by members
Have the network operators provided a formal explanation for why the solar farm has been shut down?
National Grid Electricity Distribution (NGED) have confirmed the distribution and transmission network operators have been aware of potential voltage issues on the North Devon network since 2023. The risk of voltage issues has increased as Langage gas power station, which was being used to control volage levels, is off-line for maintenance for 2 years.
To mitigate this, the National Energy System Operator (NESO) commissioned a voltage compensation generator at Taunton and a refurbished generator at Exeter which were due to be installed by the end of 2025. However, implementation of these generators was delayed and they are now due to complete in September 2026. NGED have confirmed the works are currently on track but tests will still be required once they are commissioned
NESO became concerned about imminent voltage rise risk on the transmission network in May this year. Until the delayed voltage compensation generators are installed and tested, the only solution available to NESO to control voltage levels was to instruct National Grid Electricity Transmission (NGET) to switch off a super grid transformer (SGT) at Alverdiscott near Barnstaple.
With the SGT at Alverdiscott switched off, the local 132kV distribution network has reduced capacity and security and is vulnerable to thermal overload. To manage this risk and ensure safe operation of the distribution network, NGED have curtailed a number of generators connected to the 132kV ‘K-line’ between Alverdiscott and Indian Queens in Cornwall, including Derril Water Solar to 0kW export.
NGED were given no warning of the shut down. NGED then shut down Derril Water Solar and other generators on the K-line with no warning.
A planned Active Network Management (ANM) scheme would mean generators could be controlled on a real-time rather than shut down entirely. NGED recently informed us that the ANM system is now ready to deploy and may allow Derril Water Solar to begin partial export in August. Even with the ANM scheme live, high levels of curtailment are expected.
What is impact of the shut down on 2026 member payments?
The 4 month grid shut down through the summer generation period will have a significant impact on this year’s revenues. There will not be sufficient funds to make the planned member savings payments in August 2026 or February 2027.
What is the impact of the shut down and any ongoing constraints on future member payments?
We are awaiting feedback from NGED on the estimated ongoing grid curtailment that Derril Water Solar will experience once the ANM and voltage compensation generators are in place and the network is operating at full capacity. Once we have this, we will commission a specialist to produce an updated export forecast for Derril Water Solar Farm which will provide the basis for revised projections for bank loan affordability and member payments.
What is the status of discussions with Virgin Money, who provided a £20 million senior loan to Derril Water Solar Ltd
We are holding fortnightly calls with Virgin Money to keep them updated. We are looking at revised payment schedules to accommodate the reduced revenue this year.
Virgin Money are awaiting clarification of the impact of the shut down on this year’s finances, and ongoing curtailment levels, to inform updated financial projections including loan affordability.
Are the network operators looking into technical mitigation options?
NGED have investigated a range of technical mitigation options with NGET and NESO, including ANM, reactive compensation measures and review of grid risk tolerances. Distribution network ANM is expected to start coming online on a site-by-site basis in August and reactive compensation measures are expected to be completed in early September. The review of grid supply point risk tolerances is ongoing and results on this are awaited from NGED following completion of a trial.
Technical mitigation options at a site level were considered but could not offer a viable solution.
How wide is the problem. Are other solar and wind farms affected?
All generators on the 132kV line running between Alverdiscott in North Devon and Indian Queens in North Cornwall have been shut down.
Does Derril Water Solar’s insurance cover the grid shut down?
Derril Water Solar’s insurance brokers have provided formal confirmation that our business interruption insurance does not cover us for the grid shut down. This is standard practice in the renewables industry.
Derril Water Solar does have business interruption insurance for downtime caused by damage to the solar farm (e.g. lightning strike to the transformer or wind damage). Electricity network outages are not typically covered by solar farm business interruption insurance. Derril Water Solar has limited cover for network outages caused by unexpected damage to the network (capped at £150,000). However, the shut down is not caused by damage to the network so this limited cover does not apply.
Could Derril Water Solar be due compensation for the shut down?
We have sought informal legal advice from a solicitor specialising in renewable energy connections. Their opinion was that, even if there was a failure of duty by the network operators to manage the network properly and communicate with its customers, the recourse is an Ofgem complaint and a fine which would be paid into the national Redress fund, not to Derril Water Solar directly.
What steps has Derril Water Solar taken to escalate the issue
Derril Water Solar established communication with senior staff at NGED shortly after the shut down came into effect. NGED have assigned a senior manager to be the lead contact. We have continued to exchange emails and hold meetings with NGED and NGET regarding the issue including background, causes, mitigation and technical solutions and the longer-term outlook. We have also requested NGED bring NESO into the conversation. We have written to the Minister of State in the Department for Energy Security and Net Zero and local MPs and have engaged with the press including a detailed article by the Guardian on the shut down.
We will consider whether there is grounds for a formal complaint to Ofgem and what, if anything, this might achieve. If the complaint resulted in a fine to the network operators, the fine would be paid into the national Redress fuel poverty fund, not to Derril Water Solar directly.
Can I sell my shares in Derril Water?
At the moment there are no funds available for Derril Water Co-op to buy back member shares.
Shares in a co-op such as Derril Water Co-op are withdrawable (subject to director discretion and available funds) but cannot be transferred.
Where a co-op has list of members who wish to withdraw their shares and members who wish to buy more shares, it can facilitate the buy-back of shares to members wishing to withdraw and issue of new shares to members who wish to buy more. Derril Water Co-op may consider setting up such a register in future if and when the co-op’s finances are stable.
Given the uncertainty surrounding the financial position, we are not currently treating this as a priority and we will inform you if, or indeed when, we are in a position to offer buying or selling options for members.
Glossary
Active Network Management (ANM): a system used by UK electricity network operators to automatically limit or adjust the output of renewable generators, such as solar farms, when parts of the local electricity network are at risk of exceeding their operating limits.
NESO (National Energy System Operator): operates Great Britain’s electricity system, balancing supply and demand in real time and coordinating planned outages to keep the national grid secure and reliable. NESO is also responsible for strategic network planning.
National Grid Electricity Transmission (NGET): owns, operates and maintains the high-voltage transmission network in England and Wales, including super grid transformers that connect the transmission and distribution networks. The transmission network is the large pylons running at 400 kV and 275 kV (and 132 kV in some areas) that move power around the country.
National Grid Electricity Distribution, formerly Western Power Distribution (NGED): owns and operates the lower-voltage South West regional electricity distribution network. The distribution network is the 132kV lines which distribute power from the transmission bulk supply points around regions and the wooden poles running at 33kV and 11kV that move power from the 132kV sub-stations to local consumers, and local generation back up into the transmission network.
Super Grid Transformer (SGT): is a large, high-voltage transformer at a grid bulk supply point that converts electricity from the national transmission network (typically 400 kV) down to the lower voltages used by the regional distribution network (typically 132 kV).
Member onboarding with Ethex
Ethex has reached Stage 3 of the four-stage process and is now waiting on the results of the KYC (Know Your Client) checks, which is a standard regulatory step required before accounts can be opened on the platform. Once these results are in, Ethex will begin the secure upload process and move to Stage 4, the final stage: setting up your Ethex account and matching your Derril Water shares to it. We expect Stage 4 to get underway early August. Some members will not have passed KYC at the first attempt. This is not a cause for concern but typically means that further information will be requested. Ethex will be in touch with those members directly. In the meantime, you can follow progress on your account activation via this live onboarding tracker: ethex.org.uk/derril-water-onboarding-update
If you have any queries, please get in touch, The [email protected] inbox remains open.
All the best,
Derril Water Solar Co-op Board

